After submission of application in September, Iskul received notification of approval from Mah Sing Foundation for our application for funds to construct Pondok Iskul. Mah Sing Foundation had allocated RM 50,000 fund for the construction and basic furnishing of the space!
Iskul jumped into work immediately and kickstarted the purchasing of raw materials and recruitment of builders. The construction and the furnishing took a total of six (6) months. Classes commenced in the Pondok once the construction was completed in February and whilst the furnishing was in progress.
- Setting the foundation
- Side view: Skeletal of the Pondok Iskul
- View from the ground: Skeletal of the Pondok Iskul
- Inside of the Pondok Iskul with it’s plank wall erected
- The external view of the finished Pondok Iskul!
At the moment, Pondok Iskul electricity is hosted by the nearby home of our Headmistress and the registration with the SESB is underway.

Thank you, Mah Sing Foundation and all who have funded this dream!